Summary. What you inspect on handover day, how you measure it and where the pass line sits determines the final payment and the warranty. Twelve checks: dimensions, position, flatness, junctions and seams, colour and sheen, fixing, lighting, electrical safety, material verification, cleanliness, documentation and the objection window.
Acceptance is the step most often rushed and most often regretted. Without a jointly agreed checklist, 'acceptable' becomes a matter of opinion: the client thinks it is not finished, the fabricator thinks it is, and both the final payment and the warranty get stuck. The list below is what we walk through at handover. It favours neither side; it simply makes explicit what to look at, how to measure it and what counts as a pass.
1-2. Dimensions and position: measure against the drawing, not by eye
Bring the approved shop drawings on site and measure with a tape or laser distance meter: overall width and height, centre-to-centre spacing of main elements, height above finished floor. Compare each to the drawing. Then check position - is the piece on the agreed setting-out line, has it drifted into a circulation route or a sightline? Agree an allowable tolerance in the contract rather than arguing numbers on the day; convention is millimetre-scale, but the figure should be one both parties accepted in writing. Photograph the measurements and raise objections on site.
3-4. Flatness, junctions and panel seams: the parts only visible up close
These decide whether the work looks good at one metre. Check flatness with a straightedge held against the surface; on relief, look for natural transitions and for tool or patch marks. Junctions are about boundaries: where the piece meets wall, floor and ceiling, are the lines clean, is there sealant residue, exposed substrate or a ragged edge? Seams concern alignment between adjacent panels - consistent gap, matching pattern across the joint. Large murals and panel-assembled relief deserve particular attention here, since a good individual panel does not guarantee a good assembled whole. Inspect from the normal viewing distance, then step one metre closer.
5. Colour and sheen: look under three lighting conditions
Colour is the most disputed item because it changes with light. Daylight, normal mall lighting and dedicated accent lighting can give three different readings, while the client usually sees only one of them. Carry out acceptance under the conditions in which the piece will actually be used: lit displays are accepted switched on, daylight-dependent walls are viewed in daylight. Check for visible colour variation within one plane, uneven sheen, missed coating and runs. A small approved colour sample retained from production is far more reliable than memory.
6. Fixing and stability: push it, look at the hangers, think about tipping
This is a safety check, not an appearance check. Push lightly at the top of a floor-standing piece and watch for movement. For suspended work, confirm hanger positions match the drawing, connections are tight and locking provisions exist. Tall slender forms need a weighted or fixed base with anti-tip capacity. In public spaces add one more layer: visitors touch and children climb, so edges within reach should be rounded or padded and sharp projections removed. Ask for the installation record or a self-inspection sheet for structural elements and keep it on file.
7. Lighting: accept it during the lit period
Accepting a lit installation in daylight is not accepting it at all. Schedule a separate check with the lighting on and review four things: overall brightness against expectation, consistent colour temperature (mixed batches are the classic fault), dark zones or blown-out hotspots, and exposed or glaring luminaires. Then check controls: accessible switching, sensible circuit separation, no flicker. Run every programmed or interactive mode, not just the default. Lighting faults usually require disassembly to fix, so finding them later costs far more.
8. Electrical safety: concealed cabling, earthing, no abnormal heat
A client need not be an electrician to check a few things: are all cables concealed or in trunking, is any temporary wiring exposed, are joints insulated, does the distribution box open normally and carry labels? After the system has run for a while, carefully feel near transformers and connections for obvious heat. If the site has an electrician or engineering team, inviting them to a powered inspection is the cheapest route. For high loads or multiple circuits, confirm independent residual-current protection. A fault here affects more than the display.
9-10. Material verification and cleanliness: against the quotation, and back to original condition
Take the delivery-day material list and check brand, model and specification item by item. It takes minutes and prevents the most expensive class of problem: substitution. If no delivery record exists, at least verify visible components and offcuts. Then check two kinds of cleanliness: the finished surface itself (no adhesive marks, fingerprints, drips, footprints) and the surrounding area (protective film removed, walls unmarked, common facilities undamaged). Derig cleaning directly affects the mall's acceptance and deposit return, so allow a dedicated half day for it.
11-12. Egress, documentation and the objection window
The last two items are routinely skipped yet protect both the final payment and the warranty. Check that the display does not occupy an escape route, that clear egress width is maintained, and that sprinklers and detectors are unobstructed - ideally confirmed with the site operator, who is the final judge. Obtain four documents at handover: as-built drawings or completion photographs, a material and luminaire schedule for future replacement, care and cleaning instructions, and a warranty card stating scope and response times. Finally agree an objection window, for example three days for written notice after delivery, after which acceptance is deemed complete. That protects the client's right to inspect and the fabricator from an open-ended hold.
From the workshop
How we work
The seven-step process from brief to crated delivery, plus how quotations are built.
Read process →Export & terms
Packing, documentation, freight terms and what an overseas buyer needs to confirm.
Read terms →Three ways into the material
Technique articles explain how the work is made. Buyer insights explain how a project is specified, approved and accepted. The Q&A section answers the questions that come up before a quotation is agreed.
Technical knowledge base
22 in-depth articles on materials, processes, installation QA and applications.
Open section →Buyer insights
7 long-form guides on contracts, site access, acceptance, briefing and aftercare.
Open section →Tell us what you are building
Send photos, dimensions, the destination country and your target date. You will get a technique recommendation, a reference price band and a production schedule - no obligation.
Request a quoteHow export works